|
|
|
Large crack in the existing foundation.
|
|
|
|
Even larger crack in the existing foundation.
|
|
|
|
We had to widen the trench the existing foundation sat it to make room for forms exposing the sewer and the electrical service for the back units.
|
|
|
|
Sewer detail. It's all cast iron.
|
|
|
|
Widening also exposed the gas meters and water main on the other side.
|
|
|
|
|
Next we brought in some heavy equipment. This guy was really good with that thing. He worked it like an extension of his own arm.
|
|
|
|
He dug all our footings out that he cold reach including the front wall.
|
|
|
|
We also lifted the house another 3 inches.
|
|
|
|
Ordered up some forms and rebar.
|
|
|
|
Forming up the front wall. The existing front wall will serve as an internal form. I hung all that rebar in there. I was practically
upside-down.
|
|
|
|
|
Side wall partially formed with rebar.
|
|
|
|
Rebar cutting and bending tool. That no. 5 rebar is really hard to cut.
|
|
|
|
View from our porch.
|
|
|
|
Bracing for the front wall in case it decides to give up after 90 years.
|
|
|
|
Sewer stub wich will run through the new foundation. It's wrapped in foam that serves as an expansion joint between the concrete.
|
|
|
|
|
We exposed some of the rear units utilities while digging the foundation. We had to wrap those too with foam for expansion.
|
|
|
|
Bottom of the side footing with rebar.
|
|
|
|
Back corner of the house.
|
|
|
|
Completed framing with rebar and supports
|
|
|
|
Pins that hold the forms from busting out
|
|
|
|
|
All ready for concrete!
|
|
|
|
Here's the truck!
|
|
|
|
Here's the concrete pumper guy doing his thing, filling our forms up with glorious concrete
|
|
|
|
All filled. Now we have to smooth out all the tops for the plates.
|
|
|
|
Anchor bold holder with taped up anchor bolt.
|
|
|
|
|
There's our anchor bolt!
|
|
|
|
Well, the concrete has sat long enough so lets take the forms off!
|
|
|
|
Ooooooooo! Get a look at that new front foundation!
|
|
|
|
Hoooooowoooo! Look at those walls!
|
|
|
|
Yeah, I feel that way too Rob! Totally spent after a hard day of work.
|
|
|
|
|
But just look at that beauty of a foundation! She's all ready for some serious framing now boy!
|
|
|
|
Not too often that we get this in our driveway! He JUST fit down here.
|
|
|
|
Elias REALLY wanted to get involved with that BIG truck!
|
|
|
|
He was dropping off sand for our new slab and some crushed and washed granite for backfilling the foundation and the french drains.
|
|
|
|
After all that, I got to drill and seat the anchor bolts in our new plates. We put a bunch of
adhesive underneath them to seal out bugs and water.
|
|
|
|
|
Next we placed in the cripple wall to raise the floor off the foundation. Notice that this allowed us to remove the temporary walls!
I think it's framing time! |
|
|
|
Having to add some more more foundation slides. This is a picture of a footing I dug (1 of 3) 24"x24"x24" for piers. The small hole is the old one.
|
|
|
|
Finally got the french drain on the side yard. Had to chip out the curb to make way for the drain pipe.
|
|
|
|
Coated the media room floor with waterproof membrane and installed expansion joints.
|
|
|
|
Added a layer of sand and then cut rebar. Nice pose Rob!
|
|
|
|
|
Rented a cement cutter and cut the driveway out where piers and grade beams will go.
|
|
|
|
Spent all weekend digging this out. 1 foot deep on the grade beams and 2 feet deep for the piers.
|
|
|
|
Poured pier in the basement.
|
|
|
|
Poured front porch.
|
|
|
|
Front porch foundation detail.
|
|
|
|
|
Piers for the big deck.
|
|
|
|
Also poured the slab in the media room.
|
|
|
|
Pier detail. This will hold a 6x6 that supports the big deck.
|
|
|
|
Forming up our protective curb and laying rebar for the driveway we had to take out.
|
|
|
|
Finished curb with the french drain outlet.
|
|
|